Lean Construction Ireland Annual Book of Cases 2021 71 l f s s 2 and the retention of resources. The newly formed mobilisation team completed brainstorming sessions and identified several areas where mobilisation opportunities lay as well as the ease of pre-implementation. The two key areas that the team identified for improvement were: • The early identification and onboarding of resources required. • The reduction of the number of unsuitable candidates proposed for the roles. To improve the identification of resources required, the team determined that a Q-3 forecasting process could be developed allowing for early identification of key roles. For the reduction of unsuitable candidates, the team determined that a four-point plan would be needed as follows: 1. Role justification and approval: Departments had different methods of role approval. The team determined that a standardisation of this system was justified. 2. Job descriptions and onboarding documentation: A review of the job descriptions (JD’s) and onboarding documentation identified that several JDs were being rewritten for each role. The team determined that a 5S exercise would be carried out to reduce the variability of the JDs. 3. Centralised document storage: The team determined that there was low compliance to the centralised storage of mobilisation documentation.The team resolved to complete an industry review and implement a centralised system for all departments.The team also determined to integrate and manage standardised reporting using an agreed system. 4. Improving the relationship with resource providers: The team decided that proactively improving the relationship with resourcing providing partners,would improve the ability to identify the required preferred resources more efficiently. At this point the team subdivided the challenges and focused on measuring the current status. Measure To set the benchmark, the mobilisation team reviewed the current mobilisation process and determined the major Key Performance Indicators (KPI’s) as being: • The time tomobilise a resource from approval to onboarding. • Ameasurable reduction in the handoffs required to mobilise a resource. • A reduction in the variability of the number of documents required for the process. • An improvement of Right-First Time (RFT) candidates for roles. Any improvements made in the mobilisation process would need to result in an improvement of their KPI’s. Current Status of Mobilisation: A review of the existing time to resource and onboard a candidate through the various phases was competed and a duration of 17 weeks was identified. Figure 1: Typical resourcing timeline (Pre-improvements) Current Status Handoffs:A process map of the handoffs required to mobilise a resource showed that up to 8 stakeholders were involved in the process with up to 28 handoffs needed to identify a resource and an additional 22 handoffs in the mobilisation needs. Figure 2: Previous Onboarding process swim lanes Current Status Documentation: A review of the number of Job Descriptions (JDs) identified a total of 228 unique JDs,many of which were for similar if not the same positions.A review of mobilisation documentation identified 12 unique mobilisation documents used in various departments. Current Status RFT candidates: The team reviewed the ratio of CV’s submitted to the number of candidates hired and determined that a 34:1 Ratio was the highest ratio for the most difficult roles. This resulted in a total of 30-80 hours of time (3-8 working days) required for the hiring managers to hire a candidate for a position. Any reduction in this time would be considered a significant improvement.This led to the establishment of the following KPI’s to improve on inTable 1. Table 1: Initial Current state Analyse The ATG mobilisation team dived deeper into the root causes for the variability and determined that the overall cause was the independent nature of the hiring processes within each department and the autonomy given to each hiring manager to determine their own requirements.The mobilisation team determined that any output generated from the exercise would result in a Standardised Operating Procedure (SOP) with control of mobilisation being owned by the mobilisation team.The team determined their target goals as being those outlined inTable 2 and set about with the required improvement process. Improve For documentation and hand off improvements, a 5S process was used.An example of its use was the analysis of the existing tracking process to determine what items could be improved to collaborate Case 17
RkJQdWJsaXNoZXIy MTIzMTIxMw==